MO-602 · FY2026 Continuum of Care

NOFO Hub

Current local competition dates, applicant steps, project guidance, and submission resources for Jasper and Newton Counties.

Final timeline dated September 21, 2026 · 342 KB Word document

Competition status

Resumed September 18

Local work continues from the point where it paused. Appeals are complete.

Applicant notice

September 23

Final Priority List and written decisions go to all applicants.

Final applicant deadline

September 25

Complete directed e-snaps revisions for Collaborative Applicant review.

Public posting and local target

September 28

Post the draft package, complete Board action, and preserve the submission buffer.

Current schedule

September milestones

See every local competition date →
Fri 9/18

HUD reopens the NOFO; local competition resumes from the point where work stopped.

HUD reopening notice. Resume with Final Priority List distribution; appeals are complete.

Wed 9/23

Final Priority List distributed/posted; written notice sent to all applicants identifying accepted and ranked, rejected, or reduced applications and, if applicable, reasons.

Website and email to all applicants. This preserves the HUD 7-day notice requirement.

Wed 9/23 – Fri 9/25

Applicants revise e-snaps project applications as directed due to recommended funding reductions, technical review clarification, appeal outcomes, or rank/review conditions.

e-snaps. No changes after final applicant due date unless directed.

Fri 9/25

Final applicant deadline to complete project applications in e-snaps for Collaborative Applicant review.

e-snaps. Recommended internal lock date.

Mon 9/28

Post draft CoC Consolidated Application, Priority Listing, and project listings for public review, including accepted/ranked, noncompetitive, and rejected projects as applicable.

The Homeless Coalition website; email notice. Keep dated screenshots.

Mon 9/28

CoC Board reviews and votes/approves final Consolidated Application package and Priority Listing for submission.

Board meeting / email vote. Address final comments before internal deadline.

Mon 9/28

Collaborative Applicant internal submission target: full application packet, CoC Application, Priority Listing, and ranked project applications ready/submitted in e-snaps.

e-snaps. Revised local target date; preserves buffer.

Wed 9/30

HUD-determined final submission deadline for FY2026 CoC Consolidated Application package.

e-snaps. Due by 8:00 PM Eastern Time / 7:00 PM Central Time.

Official records

NOFO documents

Local competition schedule

FY2026 CoC NOFO Local Competition Timeline

The September 21 revision includes the HUD reopening, applicant notification and revision period, public posting, Board action, local submission target, and final HUD deadline.

Published September 21, 2026 · 342 KB Word document

Rank and Review Committee

FY2026 Post-Appeal Allocation Letter

The final post-appeal priority list records updated scores, project status, recommended funding, and reallocated funds determined by the Rank and Review Committee.

Published September 21, 2026 · 2 pages · 138 KB PDF

Questions and technical assistance

Contact the Collaborative Applicant

Josh Shackles · jshackles@escswa.org · (417) 627-2019

NOFO contact details →